Drinkwater to Coteau Creek Reinforcement Project

Share Drinkwater to Coteau Creek Reinforcement Project on Facebook Share Drinkwater to Coteau Creek Reinforcement Project on X (formerly Twitter) Share Drinkwater to Coteau Creek Reinforcement Project on Linkedin Email Drinkwater to Coteau Creek Reinforcement Project link

We’re planning a new 230-kilovolt (kV) transmission line in southern Saskatchewan to help strengthen Saskatchewan’s power system as the province grows and new sources of power generation come online.

Project Details

The project will connect the new Drinkwater Switching Station near Belle Plaine to the existing Coteau Creek Switching Station. The transmission line will be approximately 210 kilometres long.

We Want Your Feedback

Public engagement is important to us.

We’ve identified several potential route options for the new transmission line. At this stage, each option is shown within a 300-metre-wide planning corridor to provide flexibility as studies are completed and feedback is gathered. The final transmission line right-of-way will be 40 metres wide.

We’re seeking input from Rightsholders, Indigenous communities, landowners, municipalities, stakeholders and community members to help us better understand the area and identify potential concerns and opportunities.

Your feedback, along with technical studies, environmental and archeological reviews and land use considerations, will help us select a preferred route and reduce potential impacts wherever possible.

What We’re Looking for Feedback On

As we learn more about the project area, we’d like to hear from you about:

  • The proposed transmission line route options
  • Environmental, wildlife and heritage resources
  • Existing and future infrastructure in the area
  • Potential project impacts and how they can be reduced
  • Local knowledge and land use considerations
  • Individuals, groups or organizations we should engage with
  • Any questions or concerns you would like to share

How to Get Involved

There are several ways to share your feedback.

Attend an Open House

Join us at one of our open houses to learn more about the project, ask questions and speak directly with members of the project team.

Date & TimeLocationAddress
Nov. 16, 17 - 10 am to 6 pm
Nov. 18 - 11 am to 6 pm
Moose Jaw

Heritage Inn,
1590 Main Street N

Nov. 19, 20 - 11 am to 6 pmOutlookOutlook Civic Centre,
520 Semple Street


Use Our Map Tool

Drop a pin on the map and let us know your insights on areas that are important to you using our map tool.


Submit a Feedback Form

Complete this form to share your feedback on the line routes and let us know how the project will impact you, your operations, and your community.

We’re planning a new 230-kilovolt (kV) transmission line in southern Saskatchewan to help strengthen Saskatchewan’s power system as the province grows and new sources of power generation come online.

Project Details

The project will connect the new Drinkwater Switching Station near Belle Plaine to the existing Coteau Creek Switching Station. The transmission line will be approximately 210 kilometres long.

We Want Your Feedback

Public engagement is important to us.

We’ve identified several potential route options for the new transmission line. At this stage, each option is shown within a 300-metre-wide planning corridor to provide flexibility as studies are completed and feedback is gathered. The final transmission line right-of-way will be 40 metres wide.

We’re seeking input from Rightsholders, Indigenous communities, landowners, municipalities, stakeholders and community members to help us better understand the area and identify potential concerns and opportunities.

Your feedback, along with technical studies, environmental and archeological reviews and land use considerations, will help us select a preferred route and reduce potential impacts wherever possible.

What We’re Looking for Feedback On

As we learn more about the project area, we’d like to hear from you about:

  • The proposed transmission line route options
  • Environmental, wildlife and heritage resources
  • Existing and future infrastructure in the area
  • Potential project impacts and how they can be reduced
  • Local knowledge and land use considerations
  • Individuals, groups or organizations we should engage with
  • Any questions or concerns you would like to share

How to Get Involved

There are several ways to share your feedback.

Attend an Open House

Join us at one of our open houses to learn more about the project, ask questions and speak directly with members of the project team.

Date & TimeLocationAddress
Nov. 16, 17 - 10 am to 6 pm
Nov. 18 - 11 am to 6 pm
Moose Jaw

Heritage Inn,
1590 Main Street N

Nov. 19, 20 - 11 am to 6 pmOutlookOutlook Civic Centre,
520 Semple Street


Use Our Map Tool

Drop a pin on the map and let us know your insights on areas that are important to you using our map tool.


Submit a Feedback Form

Complete this form to share your feedback on the line routes and let us know how the project will impact you, your operations, and your community.